We’re still on schedule! Here are more specific dates to look forward to:
Royal Bay
March 12th – 3 Design/Build teams will be selected from their RFQ’s & move to the RFP stage.
May 31st – Deadline for 3 Design/Build teams to submit their designs for RFP.
June 25th – Winning design/team is selected.
August 1st – Anticipated start of construction at the Royal Bay site!
Glen Lake
May 2nd – Deadline for 3 Design/Build teams to submit their designs for RFP.
May 21st – Winning design/team is selected.
July 2nd – Anticipated start of construction at the Glen Lake site!